Proposed construction schedule

  1. review all mechanical changes proposed
  2. document existing facilities status with pics and notes
  3. remove/modify existing walls/drywall/carpet/electrical to suit
  4. paint walls background colour
  5. install main framework supports
  6. install staging yards
  7. wire all staging track sections
  8. install staging switch machines
  9. install low voltage power distribution network for trackage
  10. install mains framework
  11. install cork roadbed
  12. install track mains
  13. wire all track sections
  14. install 115v power distribution
  15. install power supplies and breakers
  16. install switch machines